Roadwork on the Las Vegas/San Pedro Creeks Drainage Project will require a change in the traffic pattern on Calle Real west of Fairview Avenue beginning Monday, March 9 to relocate a sewer line. This traffic switch will allow for construction on the San Pedro Creek Bridge scheduled to begin next month. Drivers, pedestrians, and cyclists are urged to consider alternate routes. This traffic pattern will be in place through January 2016.
This project will improve the capacity of two large drainage culverts located along Las Vegas Creek and San Pedro Creek at U.S. Highway 101 near Fairview Avenue. It will also prevent flooding north of Calle Real and will reconstruct the Highway 101 southbound off-ramp at Fairview Avenue. This $17 million project is 50% complete and is expected to be done by the end of 2016. More information on this project can be found on the Caltrans website.